Photo by Arturo Salcido (@EngineerSalcido)Photo by Arturo Salcido (@EngineerSalcido)Photo by Arturo Salcido (@EngineerSalcido)Photo by Arturo Salcido (@EngineerSalcido)Photo by Arturo Salcido (@EngineerSalcido)Photo by Arturo Salcido (@EngineerSalcido)Photo by Arturo Salcido (@EngineerSalcido)Photo by Arturo Salcido (@EngineerSalcido)Photo by Arturo Salcido (@EngineerSalcido)Photo by Arturo Salcido (@EngineerSalcido)
Planning a cell to 100% utilization guarantees a queue. With real variation, wait time climbs steeply past ~85% load. Going from 85% to 95% can triple it. Leave slack on purpose, then cut variation to earn it back. What utilization do you plan your cells to? #Capacity #IE
1
2
294
Building ahead because the line was running well feels like a win. It's overproduction. The extra parts eat rack space, hide the next problem and lock in parts that might change. Hit the plan early? Spend the time on the fix you never get to. What does your team do with it?
2
Arturo Salcido retweeted
Inside a Fill Machining Cell Follow NADCA for more die casting footage.
4
23
1,050
Raising strokes per minute on a press line only helps if the die can hold the new rate. Watch misfeeds, slug pulling and burr height for a full coil before you keep it. A faster line that stops twice an hour makes fewer parts than a steady one.
2
Today's Shop Floor Showdown daily at Principal Engineer: 4,750/4,750, 5/5 in 24.3 s. Casting and constraints, including where scrap hurts most: after the bottleneck, it's lost throughput for the whole plant. Your move: ieshowdown.com/?vs=48-pI-475…
6
The first shift after a holiday shutdown isn't a normal shift. Plan it like a small launch. Warm up hydraulics, re-check first piece on every die and fixture, and keep maintenance on the floor for the first two hours. Most restart scrap happens early.
5
Arturo Salcido retweeted
Most dimensional problems in a body shop get blamed on the weld robot. A lot of them start at the fixture. A quick refresher on the 3-2-1 rule: 🧵
1
1
6
Trace one shift of a material handler's path on the layout. One pen line per trip. The knots show where a closer drop point or a small supermarket pays for itself. Walking is work, and it never shows up on the standard. Where do your handlers walk the most?
1
Happy Thanksgiving to everyone keeping lines running today, and to everyone home with family. Grateful for the operators, techs and engineers who make the floor better one small fix at a time. Thank you for reading and sharing what works.
2
Walk the line before you read the downtime report, not after. The report shows what got coded. The floor shows what got worked around: the extra tote, the part staged early, the stop nobody calls in anymore.
1
An empty outline on a shadow board is the cheapest audit on the floor. If the same spot is empty every morning, it's not a discipline issue. That tool lives somewhere else for a reason. Find out why, then move the board, not the tool.
If a kanban loop never runs empty, it has too many cards. Extra cards hide the real problems: late deliveries, long changeovers, bad parts. On an EV battery module cell, pull one card a week until the loop gets tight, then fix whatever shows up.
3
The worst hour on a lot of lines is the first one after shift change. Tools moved, the open issue lives in someone's head, and 20 minutes go to catching up. A five-line handover sheet at each EV cell, filled in before the crew walks, fixes most of it.
1
Want shorter lead time? Count the WIP first. Little's Law: lead time is WIP divided by output rate. A drive unit line with 400 housings queued between ops, building 50 an hour, carries 8 hours of lead time no matter how fast each station runs. Cut the queue, not the cycle.
1
Short stops cost more output than breakdowns, and most never get logged. A 40-second jam on an EV stator winding line won't make the downtime report. Fifty of them a shift is over 30 minutes gone. Track stops by count, not just minutes. What's your cutoff for logging a stop?
2
An error-proofing sensor that operators bypass isn't a discipline problem. It's a design problem. If the poka-yoke adds a step or trips on good parts, people will find a way around it. On an EV battery module line, check its false-reject rate before blaming the team.
1
A die change on an EV casting cell isn't done when the new die is clamped. It's done at the first good part. Cold-die warm-up shots are changeover loss. Log them that way, and preheat the die off-line. How many shots until your first good part? #DieCasting #SMED
3
Rank scrap by dollars, not by count. A bin of 200 trimmed brackets can cost less than three large EV castings scrapped after heat treat and machining. Fix the expensive ones first. Everything you added before the reject is what you lose.
3
If the standard work sheet doesn't match what the operator actually does, one of them is wrong. Usually it's the sheet. Stand at the station for ten cycles, write down the best repeatable method, then train every shift to it. When did you last walk your sheets?
A time study with five cycles isn't a standard. It's a guess with a stopwatch. Split the job into elements, time enough cycles to cover the variation you see, and write a reason next to every long one before you toss it.
3