Official #Odisha Government account for news, updates and detailed information on relief and restoration activities post #CycloneFani

Odisha
Joined May 2019
For details on post ‘Fani’ restoration and the amazing stories behind the same , please visit fanirestoration.com
4
29
Faced with severe odds from nature, #Odisha Government geared up for the greatest pre-cyclone evac-op ever undertaken. Watch the @NatGeoIndia special tonight at 9PM to see how in unfolded. #OdishaFightsFani
2
8
44
11 KV Satapada Trunk fdr(22km) stringing completed after linking Dahikhia bridge today.#FaniRestoration
3
27
Banyan tree survived after replantation.#FaniRestoration
3
42
25KV DP work started for Jaliapada DT under Karamala fdr Kansa Puri Division. #FaniRestoration
3
18
Permanent restoration of Chandaka-Nimapada 132 KV line.#FaniRestoration
1
1
16
Fabrication works at Sakhigopal structure.
2
24
NESCO Transformer Repairing team.We salute them for their dedicated work in FANI. #FaniRestoration
1
4
26
Tower erection in full swing at location no 48 of 132kv Nimapda Puri line as on 3pm of 10th June. Expected completion of 85% by TODAY.#FaniRestoration
2
3
19
Efforts are on for saving the trees damaged during ‘Fani’ by the officials of Forest Department. Their dedication to save the green cover is commendable .#FaniRestoration
2
8
Restoration of a partially uprooted Banyan tree in Bhubaneswar.Large no. of such trees are being restored in Cuttack, Puri and Khurda District in Government and private land.#FaniRestoration
3
15
2
116
A Big cheer for the power restoration teams. In BHUBANESWAR COMMAND AREA, due relentless efforts of all concerned motivated, engineers if OPTCL and PGCIL could revive all the affected links and make the system permanent with the FINAL closure from PGCIL TODAY.#FaniRestoration
2
13
1
124
Sequence of events on revival of all permanent power link in Bhubaneswar 1. 220kv MDSL-CDK LINE 3/4: 20th May 2. 220kv ATRI-N.pur LINE 1/2: 28th/29th June 3. 220kv MDSL-CDK LINE 1/2: 1st June 4. 132kv MDSL-CDK LINE: 9th June 5. 400kv Baripada-P.bil and Duburi- P.bil: 9th June.
4
20
Unloading of poles at Brahmagiri Section under Puri Division.#FaniRestoration
2
15
LT Restoration work at Jhinti village under Nimapada Division.#FaniRestoration