Marigold Infrastructure Partners is the group building the new 14km Edmonton Valley Line West rail extension – connecting the downtown with west Edmonton.

Edmonton, AB
Joined August 2021
🚧 As construction continues along the Valley Line West LRT alignment, wayfinding signage helps pedestrians, cyclists & drivers navigate safely around work areas. Stay informed about construction impacts & upcoming work by subscribing to our newsletter: 👉 marigoldinfra.ca/email-sign-…
2
78
On or around October 26, 2026, Marigold crews will be pulling rail on the south side of 87 Avenue at 182 Street during overnight hours (12:15 a.m. to 5 a.m.). MORE INFO: tinyurl.com/4cszy4j2
82
🚊 Progress continues at West Edmonton Mall Station! From elevated guideway construction to major roadwork, we continue building the Valley Line West LRT. Each milestone brings us one step closer to completing the line and connecting more of Edmonton.
1
112
💨 Weather Update: Environment Canada has issued a wind warning for Edmonton, with gusts up to 90 km/h expected this afternoon. If travelling near the Valley Line West LRT corridor, please use caution, watch for debris, and follow all traffic signage. Stay safe! 🚧 #YEGTraffic
215
🍻 There’s always a reason to stop by Brewsters! 🍗 Wing Night: Tues & Thurs from 3 p.m. 🌙 Late Night Happy Hour: Daily from 9 p.m. 🍺 New Paul’s Picks IPAs 🎁 $50 gift card = $10 bonus voucher! Dates TBA. 📍 11736 104 Ave NW 📲@wearebrewsters #YEG #SupportLocal
1
1
155
On or around October 28, 2026, as part of the Final Design of the Valley Line West, vehicle access on 156 Street to/from the business complex on the southwest corner of the 156 Street and Stony Plain Road intersection will permanently close. MORE INFO: tinyurl.com/bdzmw97m
105
From all of us at Marigold, Happy Thanksgiving! 🍂 We’re grateful for the Edmonton community and thankful for your patience and support as we continue building the Valley Line West LRT. What are you thankful for this Thanksgiving?
1
81
Ever wondered what those small buildings near the LRT tracks are for? 👀 Utility complexes house essential systems that help keep the Valley Line West LRT running safely and efficiently, including power supply, signalling, communications and control equipment.
1
3
93
On or around October 15, 2026, Marigold crews will be pulling rail on the south side of 87 Avenue at 189 Street during overnight hours (11 p.m. to 5 a.m.) only. MORE INFO: tinyurl.com/mrxd53zr
4
101
On Oct 15, 2026, Marigold crews will be pulling rail across the Anthony Henday Dr NB on/off ramp. MORE INFO: tinyurl.com/mutmpc45
2
90
On October 13, 2026, Marigold crews will be performing track work on 104 Avenue between 108 Street and 109 Street during overnight hours (9 p.m. to 6 a.m.). MORE INFO: tinyurl.com/mwsvhnpm
1
80
On or around October 9, 2026, Marigold crews will be performing utility work in the outside eastbound lane on 104 Avenue near 119 Street during daytime off-peak hours (9 a.m. to 3 p.m.). MORE INFO: tinyurl.com/32xfwyhs
1
2
67
Did you know planning for the Valley Line West LRT dates back to 2008? From early public engagement workshops to project development, the line has gone through years of planning to get to where it is today. Explore the detailed project timeline 👉 tinyurl.com/5xf539ky
67
⚠️ 🚧 UPDATE: On or around August 12, 2026, Marigold crews began ductbank and rail construction on Stony Plain Road near 153 Street. This work is expected to last an additional 10 weeks than previously communicated (approximately January 2027). MORE INFO: tinyurl.com/yck8w9cv
2
96
Looking for a quick bite, a casual get-together spot or some classic comfort food? 🥞🍳 Stop by @DennysDiner at 10803 104 Ave NW and support local businesses in the community! 📞 780-425-8408 🌐 dennys.ca #DineLocal #YEGEats #FamilyDining #OpenLate #EdmontonFood
83
On or around October 1, 2026, Marigold crews will begin track work at 121 Street and 104 Avenue/Stony Plain Road during overnight hours (9 p.m. to 6 a.m.) only. MORE INFO: tinyurl.com/sdyfpfx5
1
67
🧡 Today, we honour residential school Survivors, remember the children who never returned home, and recognize the ongoing impacts of the residential school system. Marigold is committed to learning, listening, and supporting the ongoing journey toward reconciliation.
1
73
UPDATE – This work has been extended to the end of the year. MORE INFO: tinyurl.com/27tmn529 To facilitate trackwork & Valley Line West LRT Stops construction, sections of Meadowlark Rd and 156 St between 87 Ave & 100 Ave will be closed. Click the link to read more.
102
UPDATE – This work has been extended to the end of the year. MORE INFO: tinyurl.com/5k2avvb9 To facilitate trackwork & Glenora Stop construction, sections of Stony Plain Road between 124 St & 139 St will be reduced to a single shared lane. Click the link above to read more.
87
UPDATE: On or around May 28, 2025, Marigold crews began periodic overnight work on 102 Avenue between 107 Street and 102 Street, in addition to the ongoing daytime works. This work has been extended to last until the end of the year. MORE INFO: tinyurl.com/2uzbatz5
76