530+ Bengaluru projects are in the pipeline but not yet in the market. None of them is in the unsold-stock counts research houses publish.
We map them by micro-market: North, East, Sarjapur Road–ORR and South.
Full record: brei.in/pipeline
#BREI
3
1,510
When Bengaluru's e-khatas went online, about 21.5 lakh draft records were published.
The split:
About 6.5 lakh were B-khata, roughly three in ten. Taxed, but not meeting layout and building rules. They move to A-khata only through conversion.
1/2
#BREI
1
9
5,878
A khata is a property-tax record. It shows who pays tax, not who owns the land or whether the building was approved.
A-khata, B-khata and e-khata explained, with six checks before buying:
brei.in/bengaluru-market-ins…
Bengaluru's metro has run 103.6 km since 14 November. The stated target is more than 170 km within 18 months.
On the dates given on 11 November, it reaches ~165 km in about a year. KR Puram–Hebbal, the section that takes it past 170, is due six months later.
#BREI
1
1
1,153
Infineon's new Bengaluru campus, ~6.3 lakh sq ft at Bagmane Solarium, Whitefield, is leased from 1 December.
The split:
Infineon says it is sized for 4,500 people by 2030. It has about 2,500 across India today, and the campus absorbs its two existing Bengaluru sites.
1/2
#BREI
Trial runs have started on the ORR metro. A test train ran about 6 km from Baiyappanahalli depot through KR Puram to Doddanekundi on 10 November.
The minister had said trials would begin by end-October. Silk Board–KR Puram is still targeted for mid-2027.
#BREI
Silk Board–KR Puram, the ORR metro, is now targeted for mid-2027. In August it was March 2027. Before that, end-2026.
On BMRCL's schedule, Hebbal–airport follows at end-2027 and KR Puram–Hebbal in early 2028. Track laying on KR Puram–Kempapura has not started.
#BREI
7
1,251
The same 118 large projects from Bengaluru's listed developers booked another 2,216 homes in Jul–Sep, their K-RERA filings show.
Unsold: 12,824 to 10,524, down 18%.
Sobha's fell 13%, to 3,500. It still holds the most of any group.
#BREI
Bengaluru’s listed developers have sold 83% of 74,098 homes in large projects launched since 2022.
But here’s the catch: sales velocity is slowing.
Citywide sales fell 6–7% QoQ in Apr–Jun. Of 12,824 unsold homes, Sobha holds 4,031.
Source: K-RERA
#BREI
10
2,708
Bengaluru had about 80,200 unsold homes at the end of September on Anarock's count, up 35% in a year.
The detail worth noting:
Since June the stock rose about 1%, while quarterly sales rose 9%. It still equals about 15 months of sales, the same as in June.
#BREI
Prestige booked ₹3,927 crore of Bengaluru home sales in July–September, 54% of its quarter, its investor presentation shows. In April–June, Bengaluru was 27%.
Where it came from:
~44% of that Bengaluru figure came from two projects launched in the quarter.
1/2
#BREI
The CM's 13 November memorandum to the PM asks for early clearance of the Sarjapur–Hebbal metro.
It says the proposal first went to the Centre in January 2025 and was revised to a lower cost at the Centre's request. Central approval is still pending.
#BREI
The Sarjapur–Hebbal metro is dated April 2033 in its revised DPR. It was 2031
The Centre's nod, expected in October, hasn't come. Civil work can't start without it.
Any metro premium in Sarjapur Road prices today is for a line with no central approval and a 2033 date.
1/2
#BREI
Applications are open to regularise houses built before July 2008 on BDA-acquired land, at the halved fees. The CM has given 17 December as the last date.
The striking part:
At the old rates, about 600 applied. The state counts ~1.1 lakh such houses. Roughly 0.5%.
1/2
#BREI
Regularising a 20x30 house on BDA-acquired land will cost 5% of guidance value. A 50x80 house: 25%.
Karnataka halved every slab last week. About 1.1 lakhs houses are in scope.
The Bill has cleared both Houses and awaits the Governor's assent.
#BREI
2
8
1,669
Bengaluru's metro passes 100 km today as the Pink Line's elevated stretch opens. The minister's next target: 170 km in 18 months.
The detail worth noting:
Sections due before then take the network to ~165 km. Reaching 170 needs KR Puram–Hebbal, ~11 km, due early 2028.
1/2
#BREI
Silk Board–KR Puram, the ORR metro, is now targeted for mid-2027. In August it was March 2027. Before that, end-2026.
On BMRCL's schedule, Hebbal–airport follows at end-2027 and KR Puram–Hebbal in early 2028. Track laying on KR Puram–Kempapura has not started.
#BREI
1
10
3,805
Applications are open to regularise houses built before July 2008 on BDA-acquired land, at the halved fees. The CM has given 17 December as the last date.
The striking part:
At the old rates, about 600 applied. The state counts ~1.1 lakh such houses. Roughly 0.5%.
#BREI
Regularising a 20x30 house on BDA-acquired land will cost 5% of guidance value. A 50x80 house: 25%.
Karnataka halved every slab last week. About 1.1 lakhs houses are in scope.
The Bill has cleared both Houses and awaits the Governor's assent.
#BREI
1
941
The Sarjapur–Hebbal metro is dated April 2033 in its revised DPR. It was 2031
The Centre's nod, expected in October, hasn't come. Civil work can't start without it.
Any metro premium in Sarjapur Road prices today is for a line with no central approval and a 2033 date.