Permits are a black box. We made visibility the priority.
@TurboPermit estimates approval dates from similar recent projects, provides real time status across jurisdictions, and identifies the longest lead time reviews so they can be started.
It's faster to get where you're going when you see the path ahead. Check it out below!
1
61
I love agency and action. Wrapped LA @Techweek_ and realized nothing recharges me like other founders in motion. My highlights:
1. We had an incredible turnout and an engaged group that heard from Nick, Grace, Jesse and me. Our 2nd AI for Housing gathering may have to become an annual event! Glad the topic was part of the conversation at a time when housing innovation has to happen.
2. Great experience pitching @TurboPermit at PitchLive LA with founders working on very different problems. Thanks @AlphaEdisonLA and @amplifyla for the invitation!
3
79
I’ve known we had a great product, but haven’t done much to show people what it can do.
@TurboPermit is a faster way to get housing approvals:
• Real-time status updates through city integrations
• AI Plan PreCheck to catch errors and reduce resubmissions
• Emails written, read, and acted on
• Auto-filled forms eliminating repetitive work
Our goal is simple: less time managing permits, more time building homes.
Take a look, then explore a project tour or example project on our homepage (link in 1st comment).
Eight jurisdictions. Eight unique processes.
Efficienct processes eliminate variaton and waste. Housing permitting has room to improve on both.
At TurboPermit, we’re using tech to create predictability, automate steps away, and helping builders get housing approvals faster.
Explore residential permit processes and more: turbopermit.co/approved
Atlanta, Georgia is the newest city in the @TurboPermit housing timeline insights series!
Single-Family time to approval climbed the last three years:
• 88 days in 2023
• 110 days in 2024
• 130 days in 2025
Median time to approval is substantially faster than what we saw in California.
• 𝗦𝗶𝗻𝗴𝗹𝗲-𝗙𝗮𝗺𝗶𝗹𝘆: 109 days
• 𝗔𝗗𝗨: 91 days
• 𝗧𝗿𝗮𝗰𝘁: 58 days
Review the complete analysis:
turbopermit.co/permit-approv…
2
131
San Antonio, TX housing permits are among the fastest we've seen. The start of the process is where back-and-forth is still happening. An AI completeness check at Intake helps even the fastest jurisdictions eliminate review cycles.
@TurboPermit analyzed 14,621 City of San Antonio new home permits issued since 2023.
The times to approval are impressive
• Tract homes: 𝟳 𝗱𝗮𝘆𝘀*
• Single-family homes: 𝟰𝟳 𝗱𝗮𝘆𝘀
• Middle 50% of single-family homes: 𝟮𝟯–𝟴𝟴 𝗱𝗮𝘆𝘀
*excludes plat review
It's no surprise new communities are booming in San Antonio. Tract home time to approval is accelerating. From 11 days in 2023 to 6 days in 2026 so far.
We help applicants submit cleaner permit packages so staff and builders spend less time going back and forth. We're helping jurisdictions drive toward San Antonio speed and real-time approvals!
San Antonio housing permit insights:
turbopermit.co/permit-approv…
Replying to @KenjiCapital
The typical Houston SFR is approved in 63 days. TurboPermit.co just published data on hundreds of recent housing permits. Check it out here: turbopermit.co/permit-approv…
16
What do Houston, TX and Jackson Hole, WY have in common?
Very different housing markets. Very different scale. Same lesson: quick responses.
TurboPermit has analyzed thousands of local plan review records in search of ways to reduce the timeline to put a shovel in the ground.
𝗛𝗼𝘂𝘀𝘁𝗼𝗻, one of the fastest-growing housing markets in the country, is approving typical single-family home plans in 𝟲𝟯 𝗱𝗮𝘆𝘀, with the middle 50% of permits completed in between 𝟯𝟰–𝟭𝟭𝟯 𝗱𝗮𝘆𝘀.
Houston does a good job putting the ball back in the builder’s court (follow the link in the first comment for the animated chart).
𝗝𝗮𝗰𝗸𝘀𝗼𝗻 𝗛𝗼𝗹𝗲, another fast-moving market, has a very different housing context.
For new single-family homes, the typical timeline was 𝟳𝟰 𝗱𝗮𝘆𝘀 in the Town of Jackson and 𝟭𝟰𝟱 𝗱𝗮𝘆𝘀 in Teton County. Even with local conditions and agency coordination, the process is moving much faster than the California markets we’ve analyzed.
The takeaway from both was the same. Clear inputs, handoffs, and faster turnaround times move the process forward.
That is why we built TurboPermit Intake for jurisdictions: to help applicants make complete submittals, reduce avoidable review cycles for both sides of the counter, and keep the process moving.
Houston:
turbopermit.co/permit-approv…
Jackson Hole:
turbopermit.co/permit-approv…
TP Intake for jurisdictions:
turbopermit.co/intake
2
119
Replying to @adamcarolla
Adam, we analyzed thousands of housing permits so we could help builders go faster. Check out our findings at TurboPermit.co/approved
9
We’ve kept it simple @TurboPermit. Every product decision had to help residential builders go faster. A few years in, our easy to use mobile and desktop interfaces are delivering on that objective.
On the other side of the counter, community development leaders, mayors, governors, and the President want to go faster too. Supporting jurisdictions was a logical next step for our business. I’m excited to announce our first product for public partners, Intake, an AI-powered way to improve application completeness.
As perfectly illustrated in our SD permit timeline analysis (below), a housing permit takes teamwork across private and public partners. I’m excited about what working with more public partners means for driving housing timelines down. Reach out to discuss supporting your AHJ or learn more!
1
2
146