Lunar economy brief, week of Mon Nov 16 to Sun Nov 22, 2026 (all times CT)
BOTTOM LINE
No named lunar mission moved its launch date this week. The progress
came in hardware and contracts instead: NASA posted the final RFP for
its first lunar fission reactor, Firefly added a navigation payload to
a 2028 mission, Lunar Outpost's crew rover passed a design review, and
ispace signed a laser comms study with NTT. On launch vehicles, ULA's
early finding on the Vulcan failure points at the vehicle's fuel
supply rather than the BE-4 engines, which is good news for New Glenn
and Blue Moon if it holds.
LUNAR MISSIONS
No named lunar mission changed its date this week. Where things stand:
- Griffin-1 (Voyager, formerly Astrobotic): January 2027, the
company's date. A launch database lists Jan 6 on Falcon Heavy, but
that is not a company date. On Nov 16 Voyager reported Phase II tests
of its "Floatinator" plume-surface simulator.
investors.voyagertechnologie…
- IM-3 (Intuitive Machines Nova-C "Trinity" plus the Altus-1 relay):
still March/April 2027. Altus-2 to -5 are still 2028.
- Firefly Blue Ghost Mission 2 (far side plus Elytra): 2027, no change.
- Firefly Gruithuisen Domes mission: NET 2028. On Nov 17 (7:00 AM CT)
Firefly signed QASCOM to fly its COLLINS navigation payload on Elytra
Dark in lunar orbit for six months. The mission now carries eight
payloads, six through CLPS.
investors.fireflyspace.com/n…
- ispace Mission 3 (ULTRA lander): still 2028. Mission 2.5 relay
orbiter: NET 2027.
ispace-inc.com/2026/11/16/nt…
- Blue Moon Mark 1 "Endurance": early 2027 per press reports, waiting
on New Glenn's return to flight. A January 2027 New Glenn return comes
from a press report of an internal memo (unverified).
- Artemis III (Earth-orbit docking test with Blue Moon and Starship
test articles): mid-2027, no change. Artemis IV/V landing target is
still 2028.
- Starship HLS: no milestone this week.
- Lunar Outpost Pegasus crew rover: passed NASA's preliminary design
review on Nov 19 (8:00 AM CT), four months after its $220M award.
Flight-ready delivery to NASA in late 2027, Moon delivery in 2028.
globenewswire.com/news-relea…
- China's Chang'e-7: still postponed with no new official date. ESA
Argonaut: Nammo UK reported prototype descent-engine hot fires (single
aggregator source). JAXA/Toyota pressurized rover: JAXA's president
said it aims for fiscal 2031 (single aggregator source).
- LEGS lunar ground stations: no award found.
1
66
WHAT MATTERS THIS WEEK
1. Lunar reactor procurement is live. NASA Glenn posted the SPARC
final RFP (80GRC027R0005) on Fri Nov 20 at 1:12 PM CT. Offers are due
Mon Dec 21 at 4:00 PM CT. The first task, LR-1 Phase 1, is a 20 kWe
fission power system with at least five years of maintenance-free
operation, "ready for launch by December 2030." Phase 1 is design to
PDR plus an electrically heated test unit within 18 months. GovTribe
reports a $350M ceiling, questions due Dec 4, and first awards
estimated around April 15, 2027; I couldn't confirm those numbers from
NASA directly. Why it matters: night-time power at the South Pole is
one of the biggest gaps for a Moon base.
sam.gov/workspace/contract/o…
2. Vulcan cause is narrowing. ULA said on Wed Nov 18 (10:00 AM CT) the
early cause is "inadequate fuel supply from the vehicle to the BE-4
engines, not from the performance of the engines." Centaur V and the
solid boosters performed as planned. Blue Origin said it identified
the same cause. Nothing is final and there's no return-to-flight date.
If it holds, the risk to New Glenn, Blue Moon, and Centaur V (which
NASA is weighing for SLS) goes down, but Vulcan stays grounded and
heavy-lift supply stays tight.
blog.ulalaunch.com/blog/vulc…
3. Starship is still waiting. SpaceX's Flight 15 page still says the
booster's boostback "ended early due to low fuel mass, with the root
cause under investigation." There's no Flight 16 date. On Nov 19 (2:38
PM CT) SpaceX responded to Mexico's reports of Flight 15 debris at
Playa Bagdad, saying partners found "very little debris" not clearly
from SpaceX. spacex.com/launches/starship…
4. Lunar comms and navigation got two building blocks: the
Firefly–QASCOM navigation payload (GNSS plus LunaNet signals in lunar
orbit) and the ispace–NTT study of Earth–Moon laser comms and lunar
laser power transmission (no money or dates attached).
5. Not lunar, but notable: Voyager 1 reached one light-day from Earth
on Wed Nov 18 at 4:16:07 AM CT, confirmed from its carrier signal.
NASA hasn't received science or engineering data from it since Nov 14.
nasa.gov/news-release/nasas-…
TEXAS, SPACEX, TESLA
- Starbase compute campus: TCEQ issued an air permit on Nov 16 for 35
gas turbines (750 MW). On Nov 17 Cameron County commissioners voted
3–2 not to hold a hearing on a 10-year tax abatement. Starbase's own
commission takes up an abatement Dec 9. (Reported by the Brownsville
Herald and Fortune.)
- Arizona: on Nov 19 AG Kris Mayes asked Cochise County to delay its
Dec 9 vote on SpaceX's data-center permit, citing up to 6 GW of
demand. azag.gov/press-release/attor…
- These are AI-compute items, not lunar work; they matter only as
competition for SpaceX's capital and attention.
- SpaceX–Tesla merger: still reports from unnamed sources only, with
no deal or filing. HSBC upgraded Tesla to Hold on Nov 20 on merger
potential but said the "business logic for a merger is not immediately
clear."
- Firefly is based in Cedar Park, Texas (see the QASCOM item above).
- San Antonio: no new lunar item this week. UTSA's $1M icy-regolith
award (Nov 5) and SwRI's proposed lunar test site remain the local
context.
1
66
SPACE WORTHY #22 (Simone Cortesi, Nov 21)
Its lunar-relevant facts check out against primary sources: the Ship
42 catch, the Booster 22 loss, and the Vulcan failure. It's out of
date on Vulcan (it doesn't have ULA's Nov 18 fuel-supply finding), and
it has no lunar-mission news. Several non-lunar lines, including stock
prices, weren't checked, so it doesn't get a blanket "verified."
MARKET BACKDROP
AP reported the S&P 500 fell 3.7% on Fri Nov 20, its seventh straight
loss, and the Nasdaq fell 5.3%, turning negative for 2026. Space
Worthy lists LUNR down 32.5% for the week with no matching company
news; I haven't checked that price.
DATES TO WATCH (CT)
- Sun Nov 30, 2:00 PM: Hubble commercial servicing RFI responses due.
- Thu Dec 3, 10:59 PM: NASA astronaut application window closes. Also
the Arizona AG's town hall on the SpaceX permit.
- Fri Dec 4: SPARC questions due (reported).
- Wed Dec 9: Cochise County vote and Starbase abatement hearing.
- Mon Dec 21, 4:00 PM: SPARC offers due.
- Open: Vulcan final cause and return to flight, Starship Flight 16
date, New Glenn return, LEGS award.
RUMORS AND UNVERIFIED
- SpaceX–Tesla merger announcement "as early as December" (Bloomberg,
unnamed sources, Nov 12).
- Griffin-1 on Jan 6, 2027 (launch database, not the company).
- Starship Flight 16 vehicles and a first Florida launch (trackers only).
- New Glenn return in January 2027 (press report of a memo)
27
Agreed. It is so sad. I hope that SpaceX can get past these road blocks.
This is so frustrating.
SpaceX wants to build a $50 billion data and energy campus near Willcox in Cochise County. That's one of the biggest investments rural Arizona has ever been offered.
Now Attorney General @AZAGMayes wants the county to delay its December 9 vote.
The campus is dry-cooled and would use about 7 to 10 acre-feet of water a year. SpaceX has also proposed $3.6 billion in grid investments.
Asking questions is fine. Holding a town hall is fine. But telling a county to stall a project this size sends a message to every company looking at Arizona: go somewhere else.
Cochise County should make its own call on December 9.
@SpaceX, we want you here.
bizjournals.com/phoenix/news…
1
21
Jay "letterj" Payne retweeted
Here is my Tesla Lithium Refinery Flyover in Robstown, Texas. This is North America’s first industrial-scale acid-free spodumene-to-lithium-hydroxide facility.
This plant converts imported spodumene concentrate (SC-6, ~6% lithium oxide) into battery-grade lithium hydroxide monohydrate using a proprietary alkaline process (no sulfuric acid). The finished product is trucked to Giga Texas to supply the cathode plant for 4680 cells used in Cybertruck, Cybercab, Semi, and future Optimus.
Key locations are the spodumene concentrate Receiving & Storage Warehouse, Kiln + Cooler (α-spodumene → β-spodumene), Alkaline Leach (lime + soda ash) Purification & Crystallization facilities, and the Packaging & Shipment facility.
What you see is Phase 1. The site was deliberately sized for a future Phase 2. Tesla is advancing closed-loop battery recycling plans involving black mass recovery. A facility for this could be coming soon.
This facility 100% supports Tesla’s vertical integration and domestic battery materials supply chain.
Enjoy! Please share the video and subscribe to support!
Jay "letterj" Payne retweeted
What's new in Grok Bot 1.0 🚀
00:45 Team Bot improvements
01:47 Bots join your meetings
03:26 Bots take initiative
04:10 Bots learn and improve
05:19 Bots are smarter and faster
Lots of easter eggs in this one for y'all!
Grok Bot 1.0 - What's new in Grok Bot - Nov 16, 2026
Grok Bot 1.0 - What's new in Grok Bot - Nov 16, 2026
Lunar brief for Nov 9–15
Here are the highlights (all times CT).
Bottom line. Starship Flight 15 reached orbit on Nov 13 and deployed 26 Starlink V3 satellites. On Nov 14 the tower caught the ship, the first time a Starship upper stage has been caught. The booster was lost in the Gulf, and the cause is under investigation. (SpaceX Flight 15) Separately, ULA's Vulcan failed today and lost 40 Amazon Leo satellites. Isaacman said "Artemis, Moon Base, and the nation need ULA."
Lunar missions
Artemis: No date change was verified this week.
Griffin-1: It slipped to January 2027, from late 2026, according to Voyager. Voyager has two more landers planned for 2028.
IM-3 and the first Altus relay: Still targeting March or April 2027. Altus-2 through -5 will now launch together in 2028 on a Falcon 9 that NASA provides.
ispace: It finished the preliminary design review for its ULTRA lander, and Mission 3 holds at 2028. Its Mission 2.5 relay orbiter is no earlier than 2027.
Firefly: It says five Moon missions are running in parallel. Blue Ghost Mission 2 is still listed for 2027.
Blue Moon Mark 1: GeekWire reports it's planned for early next year, but Blue Origin hasn't given a date.
CLPS 2: No task orders yet. IM expects the first ones in 2027.
Innermost Loop claims checked. SpaceX's $74B in supercompute campuses is confirmed. The SpaceX–Tesla merger talks are only reported by Bloomberg, and neither company has confirmed them. The NASA Moon Base recruiting is a real astronaut-candidate call that closes Dec 3. The Voyager 1 one-light-day mark is NASA's forecast for Nov 18 at 4:16 AM.
Coming up. The final request for proposals on NASA's lunar reactor (SPARC) is expected around Nov 20. Also watch for the Vulcan investigation and the first CLPS 2 task orders.
1
1
92
Congratulations to @SpaceX and everyone involved on this 7-year journey. An idea made manifest through hard work, belief, and determination. The world will not be the same after today. SpaceX has opened a door to a spacefaring future for all mankind. We just have to be brave and committed enough to walk through it.
1
32
Live webcast of Starship's 15th flight test starts now → teapawt.org/i/broadcasts/2brajgZlO…
This is the way to look at it: an incredible opportunity for the Brownsville area. We should all support these efforts—the first steps to transform Texas.
A $24 billion data center announced for South Texas this week will make its own power from Texas natural gas, stay off the public grid, and put $220 million into Brownsville's water system. That's the model: growth that pays its own way. A blanket moratorium would push projects like this to other states. Texas should write strong consumer protections and keep building.
14
If we see a Starship launch today, it will be another engineering milestone. The Roadster demonstration earlier this year was a testament to the talent at Elon’s companies. A catch attempt for the booster and ship will be epic.
The incredible future and opportunities these companies provide for the people of Texas are staggering.
🤖 Made with AI
2
43
This is very cool. This is making an incredible product even better. I’ve used the current version all over Texas.
Introducing Mini 2, the next-generation portable Starlink. Get up to 4.5 hours of connectivity on a single charge with the quick-swap battery, or plug in with USB-C.
With built-in Wi-Fi, all you need is a clear view of the sky to get online in 60 seconds.
Preorders are now open by invitation in the US. Be the first to know when it's available → starlink.com/mini-2
18
She is amazing and I hope she gets out more in the coming months. Her knowledge of the business, and marketplace serve SpaceX very well.
134
Lunar Briefing:
- **NASA selected eight CLPS 2 vendors on Nov 7**: Blue Origin,
Firefly, Intuitive Machines, ispace-U.S., Lockheed Martin, Northrop
Grumman, SpaceX, and Voyager. The $10B figure is a **combined 10-year
ceiling, not funded revenue**. Being selected doesn't fund a mission.
NASA also raised the CLPS 1 ceiling from $2.6B to $4.2B.
- **Funded work this week:** six VADR task orders worth about $1.3B
(Arrow, Blue Origin, Impulse); a PROMISE rover delivery award to Blue
Origin ($94M base plus a $140M option that isn't guaranteed, launch
targeted for late 2028); miniCAST power components; and a 2028
Starship cislunar communications delivery task for SpaceX.
- **Starship Flight 15:** SpaceX targets **Fri Nov 13, with the window
opening at 4:45 PM CT**, pending regulatory approvals.
- **New Glenn's return to flight slipped to January 2027.** This is
**reported** by CNBC from an internal memo and **not confirmed by a primary source**.
- **No Artemis date change was verified this week.**
## What happened
1. **CLPS 2 selections (Nov 7).** NASA's contract is a 10-year
multiple-award IDIQ. Says plainly that selection doesn't fund a mission
is scaling up a larger lander and has cleanroom space for 12
spacecraft. There is an option through 2041 with a $15B ceiling. That option has not
been exercised. Use NASA's $10B base figure.
2. **PROMISE rover.** JPL will build a six-wheel, nuclear-powered
polar rover from Curiosity and Perseverance spares. It targets a
late-2028 launch and an 18-month mission, and will drill about 1 m to
survey ice. It is not related to a fission-reactor award. Payload
reports total mission cost below $400M; that figure is attributed to
Payload
3. **VADR transport and comms.** The six orders total about $1.3B,
inside a $5B ceiling that is not new spending. Launchers are Falcon 9,
New Glenn, and Terran R. Named cargo includes CAPSTONE 02 and MoonFall
drones. Payload's mission-by-mission pairings are **reported**, not
confirmed. Separately, SpaceX's Starship task targets 2028 for
deploying cislunar communications satellites. **NASA does not call
them Starlink**, and no price was given.
4. **miniCAST power.** Honeybee Robotics (storage), Redwire
(generation), and Yank Technologies (wireless transfer) won component
awards. No values were disclosed. NASA expects to solicit a fully
integrated power system in early 2027.
5. **Blue Origin GS3 and Northstar (Nov 5).** GS3 is a BE-7-powered
third stage booked for an unnamed government cislunar mission in 2028.
Blue Origin says it is not required for its lander. Company targets
are up to 10 t to TLI on the 7×2 configuration and 20 t on 9×4. Its
composite hydrogen tank was pressure-tested at **Launch Site One in
Texas**; the exact test date wasn't given. Blue Origin also unveiled
Northstar, a 715,000 lbf booster engine. Its specs are company claims,
and no flight date was given.
6. **Starship Flight 15** launches from **Starbase, Texas**. The
window runs 4:45–6:00 PM CT on Nov 13, conditional on approval.
Planned goals are catching both stages, deploying **26 Starlink V3**
satellites, and flying for more than 22 hours. It is not an HLS,
propellant-transfer, or crewed test. The earlier NET Nov 12 rumor is
superseded. ([SpaceX
post]())
7. **Firefly and AST SpaceMobile (Nov 6).** The engine and IP deal is
valued at more than $1.3B, paid in a mix of cash and stock rather than
cash this week. It supports test expansion in **Briggs, Texas**, and
AST builds BlueBirds in **Midland, Texas**. This is adjacent
commercial space, not a lunar award.
2
1
267
## LUNAR MISSIONS
- **Artemis III:** 2027 Earth-orbit lander test with four crew,
planned for 14 days. **No Artemis date change was verified this
week.** NASA's Nov 4 post recaps its Oct 23 update. The test checks
crew–lander interfaces.
- **Artemis IV:** Crewed landing targeted for 2028. No new date. Both
lander suppliers are aiming for 2028.
- **Artemis II / V:** No verified movement found, and no fresh date is asserted.
- **Starship HLS:** 2027 Earth-orbit test and a 2028
landing-capability target. Flight 15 (Nov 13, conditional) is a
separate vehicle test that matters for the reuse cadence tankers will
need.
- **Blue Moon Mark 1 "Endurance":** Late Q1 2027, **reported** from
Oct 26 remarks published Nov 2
The New Glenn January 2027 return to flight is reported, not
primary-confirmed. No Blue Moon launch date follows from it.
- **Blue Moon Mark 2:** Supports Artemis III in 2027. Crew-module
welding is reported for early 2027.
- **VIPER (second Mark 1):** By end of 2027, **reported**. It
prospects for ice and is separate from PROMISE.
- **PROMISE (Blue Moon Mark 1 delivery):** **New** award, targeting
late 2028 for an 18-month mission. It surveys resources and landing
sites.
- **CLPS 2:** **New** selection of eight vendors under a $10B ceiling
that is not funded revenue. It widens who can bid.
- **Griffin-1 (Voyager/Astrobotic heritage):** Company target is
**late 2026** (Nov 2 and Nov 7 releases). A tracker shows January
2027. **That conflict is unresolved**, and no slip was confirmed this
week.
- **Firefly Blue Ghost M2 / Lunar Pathfinder:** No verified new date.
It provides far-side delivery and relay. **Blue Ghost M3–M5 / larger
lander:** CLPS 2 selection only; no new flight orders.
- **Firefly MoonFall / Elytra:**
**New** VADR transport award with no
launch date. It scouts the South Pole.
- **CAPSTONE 02:** **New** transport award with no launch date. It is
a navigation and comms pathfinder.
- **SpaceX Cislunar Comms Demo:**
**New** task targeting 2028 on Starship.
- **Intuitive Machines IM-3 (Nova-C "Trinity"), IM-4/5/6, Altus-1:**
CLPS 2 selection. No verified date change.
- **ispace-U.S. ULTRA / Japanese ispace missions:** Now eligible as a
prime contractor, but no funded delivery and no new date.
- **Türkiye TLM-1:** Q2 2027 on Falcon 9, **reported**, from a
recycled October story.
- **Chang'e-7/8, Chandrayaan-4/5/LUPEX, ESA Argonaut/Moonlight, Korean
lander:** No movement was verified. This reflects a gap in coverage,
not confirmation that nothing changed.
## Rumors and caveats
- **Rumor (superseded):** Flight 15 NET Nov 12. Use Nov 13, which is
conditional.
- **Unverified:** that Griffin "officially slipped to Jan 31."
- **Unverified:** that CLPS 2 selection equals funded missions or $10B
in revenue.
- The New Glenn January 2027 return to flight is reported, not
primary-confirmed.
- Don't add ceilings, options, and order values into one "new spending" total.
- **Texas, SpaceX, and Starlink links** are real: Starbase, Launch
Site One, Briggs, Midland, SpaceX in CLPS 2, and Starlink V3 as the
Flight 15 payload. **No San Antonio or Tesla link** was found.
168
We need a StarLink constellation orbiting the Moon. A 13 satellite constellation could serve Lunar exploration, development and the general lunar economy very well.
BREAKING: NASA just announced a new Starship mission for its Moon Base and awarded SpaceX a spot in its $10 billion Moon cargo program.
• Starship will launch communications satellites near the Moon in 2028. The mission will help NASA develop a network linking astronauts and the Moon Base to mission control on Earth.
• Falcon 9 will launch some of NASA’s new Moon Base missions.
• SpaceX was also picked to compete for cargo deliveries to the Moon’s surface under a new 10-year NASA program worth up to $10 billion across all providers.
26
This is sad news but I'm sure the folks at Blue Origin and NASA are working as hard as they can to complete the rebuild. Better to take more time and be safe. I'd be curious where the delays are. Can they just throw more bodies at it or is it some kind of technical issues?
BLUE ORIGIN DELAYS NEW GLENN LAUNCHES UNTIL 2027
• The delay follows the May 28 explosion of a New Glenn rocket during an engine test on its Cape Canaveral launch pad
• That rocket was due to carry Amazon Leo internet satellites the following week
The setback leaves Jeff Bezos's rocket company further behind Elon Musk's SpaceX, per the Financial Times.
28