The internet can generate infinite content, but it can’t manufacture physical reality.
A data center either exists or it doesn’t. Construction is either progressing or it isn’t. Permits are either filed or they aren’t.
We’re building the evidence layer connecting digital claims to what’s actually happening on the ground.
As synthetic content scales, verified reality becomes more valuable.
Ground truth is the moat.
$NBIS | NEBIUS: 4 GW OF POWER CONTRACTED. HOW MUCH IS ACTUALLY BECOMING COMPUTE CAPACITY?
Nebius has contracted more than 4 GW of power and still targets 5 GW by year-end 2026.
But its Q3 shareholder letter disclosed an important change: some third-party capacity expected online in 2026 has been pushed into the first half of 2027.
The company also:
1. Expects 2026 revenue at the low end of its $3.0–3.4B forecast.
2. Increased expected 2026 capex to approximately $27B.
3. Moved its $7–9B ARR milestone from December to February.
Nebius says the contracts remain in place. The issue is when the infrastructure becomes available, not whether the demand exists.
We looked at what is happening on the ground.
GroundAlpha tracks 23 Nebius site records across 21 campuses. We have satellite observation histories for 17 of them.
What did we find?
- At 4 campuses, satellite observations show a stronger signal associated with building activity.
- At 7, we detected smaller physical changes.
- At 6, we found no clear structural change in the areas monitored.
These observations don’t tell us on their own whether a facility is on schedule. But they help identify where reported project progress is — and isn’t — accompanied by visible physical change.
Consider Lappeenranta, Finland.
Nebius plans to develop an AI factory there with up to 310 MW of capacity. The first phase is expected to provide 60 MW.
The project is listed as under construction.
But our satellite observations have not shown the level of structural change our model would normally expect for a project at this stage.
That doesn’t prove the project is delayed. It tells us something important: the reported construction status and the physical evidence deserve a closer look.
Why this matters:
Contracted power is not the same as energized power. Energized power is not the same as usable computing capacity.
Investors need to know how quickly announced projects are turning into real infrastructure ….site by site.
GroundAlpha helps measure that gap.
Example data below
👀
Replying to @SignalScale
Checked these against our radar + filings.
$SPCX: 0.6 -> 1.7 GW of compute in 12 months (SEC). Even with ~1 GW live, the Colossus 2 campus is still adding structure: radar index 100 -> 144 since January.
Of the other 7 flagship sites, only one gets a "building" call from us. For some it's early to tell and we keep an eye out 👁️ @alwayslearni
👇
59
We’ve been looking more closely at the physical buildout behind IREN and Nebius.
There’s a lot of discussion around neocloud valuations, GPU demand and financing. We wanted to look at another part of the equation: what’s actually happening at the underlying sites?
Here’s what our GroundAlpha monitoring currently shows.
$IREN
We’re tracking 14 site records, with 8 having measured satellite coverage. Across those 8, five currently receive a building-like radar classification.
At Sweetwater 1, the measured structural signal has increased from approximately 0.17% to 0.59% over the observation period.
$NBIS
We’re tracking 23 site records, with 17 having satellite observation coverage. Four currently receive a building-like classification.
The distinction is worth investigating, but these classifications are directional radar signals, not independent construction verification. The sites also differ in development stage and observation history.
For investors, we think this is an important additional layer of diligence.
The question isn’t just how much capacity has been announced or contracted. It’s how quickly that capacity translates into physical infrastructure, energized power and ultimately revenue-producing compute.
That’s what we’re following at GroundAlpha.
If you’d like to examine the individual sites, historical satellite observations, measured series and supporting evidence, sign up!
GroundAlpha retweeted
Most knowledge workers have been traders this whole time. They just traded hours for salary. AI is ending that arrangement and handing everyone something closer to their own trading desk.
Meltem said it cleanly last week: agents mean everybody can have a Mercuria. But she also flagged the real constraint. Prediction is getting cheap. The edge moves to whoever has the better model of the physical world—not the narrative, the actual data. Markets are forming for inputs that never had them (materials, local energy flows, physical constraints, unreported conditions). Those markets only work if someone is feeding them primary signal instead of recycled takes.
That’s the split Ground Alpha is built for.
If you want to trade or allocate on that signal: the customer side gives you structured, sourceable ground data before it becomes consensus. The stuff that isn’t in the feed yet.
If you have domain access, local knowledge, or the ability to systematically observe what’s actually happening: the Scout program is how you get paid to supply it. You’re not writing content. You’re providing the raw inputs the market can price.
Both sides are open. The information market is forming either way. You can be on the consuming side, the supplying side, or both.
Sign up for Ground Alpha:
Client: ground-alpha.com/
Contributor: ground-alpha.com/scout
GroundAlpha retweeted
We just deployed the GroundAlpha Data Center Leaderboard.
109 companies. Hundreds of tracked sites.
But this isn’t another leaderboard of announced AI capacity.
We track what is actually happening:
• Building vs. operating capacity (GW)
• Permitted, proposed and under-construction sites
• Power, zoning and environmental paperwork
• Contracted capacity and development pipelines
• Week-over-week changes in construction activity
Every company summary connects back to individual sites and underlying evidence.
The objective: distinguish what companies say they’re building from what the physical world shows.
Explore: ground-alpha.com
$TSLA $META $GOOGl $AMZN $MSFT
GroundAlpha retweeted
First crowd-funded drone site. 🚁
We’re putting the GroundAlpha model into action.
Contributors pool capital to fund the collection of real-world evidence at locations that matter to them.
Data centers. Mining operations. Energy infrastructure. Construction projects. Anything worth investigating.
Once collected, that evidence becomes part of the GroundAlpha intelligence network, accessible to members and available to interested commercial buyers, with contributors participating in its commercial value.
Our first capture: Equinix Ashburn, Performance Circle.
But this is bigger than one site or one industry.
Anyone can help decide what gets observed, fund the collection, and contribute to a growing network of distributed intelligence.
ground-alpha.com/sites/equin…
GroundAlpha retweeted
What would you like to see on the ground?
Curious about what’s happening at $NBIS, $CRWV, $AMZN — or $BXDC, following Blackstone’s $5B deal to acquire a 75.1% controlling interest in 13 AWS data center buildings, with Amazon leasing them back?
Want a closer look at data centers, power infrastructure, construction projects, mining operations, or gold miners like $NEM, $B, and $AEM — recently added to Stanley Druckenmiller’s portfolio, according to his latest 13F?
Tell us what you’re interested in.
Sign up for GroundAlpha and submit a Demand Intake with the company, ticker, or specific location you’d like us to investigate.
We’ll use community demand to help decide where to collect drone footage and other real-world evidence.
Have a question about a company? Want to see what’s actually happening on the ground?
Help us get eyes on it.
ground-alpha.com
First crowd-funded drone site. 🚁
We’re putting the GroundAlpha model into action.
Contributors pool capital to fund the collection of real-world evidence at locations that matter to them.
Data centers. Mining operations. Energy infrastructure. Construction projects. Anything worth investigating.
Once collected, that evidence becomes part of the GroundAlpha intelligence network, accessible to members and available to interested commercial buyers, with contributors participating in its commercial value.
Our first capture: Equinix Ashburn, Performance Circle.
But this is bigger than one site or one industry.
Anyone can help decide what gets observed, fund the collection, and contribute to a growing network of distributed intelligence.
ground-alpha.com/sites/equin…
300 MW planned. 50 MW in Phase 1. What happens next?
We investigated Soluna’s Project Dorothy 3 in Briscoe County, Texas.
Here’s what the filings actually say:
• 397 acres acquired.
• Up to 300 MW planned for the campus.
• First phase: 50 MW critical IT.
• $APLD Applied Digital: proposed 51% JV stake; Soluna: 49%.
• $CHRN ChronoScale: non-binding tenant LOI.
GroundAlpha has tracked the site across 8 Sentinel-1 observations from April 6 to November 15.
Key takeaway: 300 MW of ambition is not 300 MW of operational infrastructure.
We track the physical evidence behind the announcements.
Explore the site: ground-alpha.com
2
296
300 MW planned. 50 MW in Phase 1. What happens next?
We investigated Soluna’s Project Dorothy 3 in Briscoe County, Texas.
Here’s what the filings actually say:
• 397 acres acquired.
• Up to 300 MW planned for the campus.
• First phase: 50 MW critical IT.
• $APLD Applied Digital: proposed 51% JV stake; Soluna: 49%.
• $CHRN ChronoScale: non-binding tenant LOI.
GroundAlpha has tracked the site across 8 Sentinel-1 observations from April 6 to November 15.
Key takeaway: 300 MW of ambition is not 300 MW of operational infrastructure.
We track the physical evidence behind the announcements.
Explore the site: ground-alpha.com
Trust and accountability!
Wow! Just finished "Messy Jobs" by @lugaricano, Jin Li and Yanhui Wu, and I've been recommending it to everyone around me since.
It's about AI, jobs and the future economy and society
Here's the core of the book and my notes in 15 cards as a primer but you should totally read the whole thing 🧵
2
147
Neocloud stocks have been punished. But is the market pricing in an industry failure, or overlooking important differences between operators?
Consider Nebius ($NBIS)
• $981M Q3 revenue (+571% YoY)
• $38.7B in remaining performance obligations
• $7.4B in cash
• $12B in new contract value since Q3 began
The opportunity is substantial. So is the execution risk: $40–45B in planned 2027 capex, third-party capacity delays and significant infrastructure demands.
At GroundAlpha, we’re looking beyond the financial headlines.
We track 23 Nebius-linked locations, with satellite radar histories at 17. Our observations show a mixed picture of physical development… not a uniform buildout.
This is just a preview.
GroundAlpha lets investors look across the neocloud landscape, compare operators and examine whether announced expansion is translating into observable physical progress.
If you’re long, short, or reassessing a position after a major drawdown, the underlying infrastructure deserves a closer look.
Don’t just trade the narrative. Examine the evidence.
Explore GroundAlpha and sign up for access to aggregate infrastructure views and cross-neocloud comparisons:
$CRWV vs $IREN vs $GLXY vs $NBIS ….
ground-alpha.com
94
GroundAlpha retweeted
Replying to @perspez
$SLNH says it has a ~6.3 GW development pipeline [Q2 2026 earnings release, 8-K]. Here's what we can check on the ground.
OPERATING TODAY: 206 MW, all Bitcoin hosting
- Dorothy 1 & 2, Silverton TX: 98 MW [Soluna 8-K]
- Kati 1, Willacy County TX: 83 MW, fully energized 8 Sep. Tenants Galaxy Digital and Bitdeer [Q3 2026 earnings release, 8-K]
- Sophie, Murray KY: 25 MW [FY2025 10-K]
PERMITS & POWER
- Kati 2: Texas state building registration for Building 1, ~112 MW [TDLR filing TABS2027003019]
- Dorothy 3: on the Briscoe County planning agenda, nothing issued yet [Briscoe County public meeting notice]
- ERCOT Base Load classification on 266 MW across Kati and Dorothy, still pending ERCOT verification [Q3 2026 earnings release, 8-K]
SATELLITE (images attached)
- Dorothy 3: new bright radar returns just south of the existing Dorothy 1 & 2 compound, consistent with ground works [Sentinel-1 radar, 6 Apr vs 3 Nov 2026]
- Kati 2: slight change so far, with newly cleared ground next to Kati 1 [Sentinel-1 radar, 1 Apr vs 10 Nov 2026]
TENANTS
- Kati 2: non-binding LOI for 118 IT MW with an unnamed tenant. The earlier tenant's exclusivity lapsed [Q3 2026 earnings release, 8-K]
- Dorothy 3: non-binding LOI from ChronoScale. The Applied Digital JV hasn't closed yet [Q3 2026 earnings release, 8-K]
The shift to AI is real and we see groundworks, but technically the rest relies on LOIs (for now?)
@alwayslearni 👀
Replying to @PaulBPrager
MW on a slide, MW under contract, MW under construction and MW actually operating are four very different things.
We’ve been building a site-level view of TeraWulf to track those distinctions across its physical footprint.
The infrastructure buildout deserves to be measured on the ground, not just through corporate disclosures.
2
97
GroundAlpha retweeted
JUST IN: Bernstein says the grid replacement in the US is not keeping up with power demand growth
A substantial update to GroundAlpha.
The Leaderboard now brings our infrastructure coverage into a single comparative view.
You can now:
Compare operating and planned capacity across companies.
Track construction pipelines and changes over time.
See satellite-observed activity alongside project status.
Examine permitting across building, power, zoning and environmental categories.
Filter across hyperscalers, AI labs, neoclouds, miners and more.
We’re continuing to connect the dots between what gets announced, what gets permitted, and what actually happens on the ground.
Take a look at the updated Leaderboard. More improvements coming.
We're keeping a leaderboard of who is building the most, along with our model for estimating time to completion.
A lot can be cleared up just by cross-referencing sources. Coming from investigations, it's easy to see the patterns there (over-declare, random declare, UNDER-declare... lots of surprises).
@GroundAlpha0 👀
1
95
GroundAlpha retweeted
We're keeping a leaderboard of who is building the most, along with our model for estimating time to completion.
A lot can be cleared up just by cross-referencing sources. Coming from investigations, it's easy to see the patterns there (over-declare, random declare, UNDER-declare... lots of surprises).
@GroundAlpha0 👀
GroundAlpha retweeted
New in GroundAlpha: Research Notes.
We’re making the research behind our findings more transparent:
• Supporting permits and source records.
• Explicit caveats and unresolved questions.
• Clear distinctions between documented facts and potential developments.
• Direct links to underlying sources.
Don’t just take our conclusions. Inspect the evidence yourself.
GroundAlpha retweeted
Common Space picks Satellogic to build humanitarian satellite spacenews.com/common-space-p…