Replying to @Schulz_Research
SPP just put a number on it. Its FERC filing (ER27-577) caps regional funding for a new load hookup at the lesser of $500k/MW or $25M per delivery point. The customer pays the rest. Past about 50 MW, the upgrade bill is yours.
2
How a large load gets power from Ameren Missouri: over 25 MW, a $200K refundable study deposit, up to 4 projects studied at a time, results good for 6 months. At 75 MW+, a 12-year term plus ramp and an 80% minimum bill. Price land by stage, not acreage. #DataCenters
16
Replying to @SmallCapSnipa
The call is a ban on new permits, not existing ones. That splits the market: approved, powered sites gain value and everything still waiting on a permit gets a discount. KC's mayor wants a pause too, so this isn't just a Texas story.
6
Replying to @KCBizJournal
85 people for 60 units before it opens says a lot about the streetcar extension. Transit-adjacent housing priced right on Main is leasing ahead of delivery. Curious whether retail along Linwood follows the same curve.
10
Ameren's Q3 call, for anyone pricing powered land in Missouri: 2.8 GW signed, 1.2 GW in construction agreements, 4.4 GW with completed studies. Signed load ramps from late 2027 to full in 2030. In Ameren territory, the queue is the product.
13
Week 47 scoreboard: graded a 56 out of 100 (50 is typical). Travel week, boots on the ground in Arkansas touring two existing data center sites. 4-week average: 56. 17 meaningful conversations, 12 revenue meetings. Full numbers: https:/ linkedin.com/feed/update/urn…
27
Friday at the Energy & Data Center Innovation Summit at Sporting Park.
The agenda was power, grid connection, and local approvals. That's the KC market in one sentence.
Speed to power is only half the story. Permission is the other half.
I write about both in Speed to Power.
1
60
Replying to @DataCenterRadar
That's a useful benchmark: a PILOT structure with a set payment to the county and schools instead of property tax, tied to a defined first phase. Do those annual figures step up as later buildings come online, or stay flat through the term?
1
1
12
Replying to @SnglrtyFarmer
That's the right checklist: what it pays, for how long, what the city gets back, and what happens if it stalls. Those terms belong in writing before an abatement is granted, not in a side conversation after the vote.
6
In St. Louis last week walking data center infrastructure, not just reading it off a spreadsheet.
A hall tells you how the power, cooling, and connectivity actually work. Drawings help. The walk decides.
What do you look at first when you tour one?
46
Replying to @JeramyUtara
Yes. Paying for substations and lines is becoming the entry ticket. The landowners who do better are the ones who read the utility's large-load tariff before they sign, so the cost recovery is not a surprise later.
1
14
Replying to @olliesloaney
That's the spillover most site models undercount. The building gets the headlines, but the housing and retail around it feel the headcount first. Are you seeing that show up more in rents or in for-sale inventory?
12
Reading a million tokens now costs about 10 cents (Avi Hacker). A 150-page OM costs pennies to screen.
Buyers will read past the cover page on every deal now. Sellers: the footnotes in your OM are getting read. Make sure they hold up.
avihacker.substack.com/p/gpt…
55
Replying to @SnglrtyFarmer
Those are the kind of terms that make a yes easier for a council and for neighbors: cooling, noise, and a cleanup plan if the site closes. Did the Nov 10 hearing keep those caps in place?
10
Replying to @JeramyUtara
That's the first filter I use too. If the utility letter has a load figure and a date, the rest of the file gets easier to underwrite. If it's still a conversation, I treat the timeline as unknown.
1
12
The one dashboard a CRE brokerage actually needs is four views, not one screen.
1. Pipeline: which deals move today
2. Site demand: who needs power and land, and when
3. Market pulse: what to post, what worked
4. Verification brief: every claim checked against a primary source before it reaches the queue
AI can fill the cells. A human still owns the publish button.
What's on yours?
43
Replying to @JeramyUtara
That's the shift I'm seeing too. Buyers want the utility path, water story, and community file before they sign, not as a diligence item after. Sites that can show all three up front are the ones getting taken seriously.
1
12
79% of site selectors now rank power as a top factor (Site Selectors Guild via CRE Daily). In 2024, workforce was #1. Over half say weak power alone gets a site cut.
Selling land or industrial? Document the power before you list.
credaily.com/briefs/power-ac…
35
Replying to @SnglrtyFarmer
Agreed. The LOI shows the demand is still there. The towns that come out ahead will be the ones that put bill protection and water terms in writing before the next vote, not after.
8
Replying to @sgfcitizen
The detail to watch is the definition. The mayor's amendment defines large load by megawatts, not square footage, and separates IT equipment from other uses. Whatever Springfield adopts Nov. 30, other Missouri cities will likely borrow. Where should the threshold land?
22